Remedial
Actions Operations,
FT-31/West POL Yard |
Bhate received notification from Holloman
AFB in early March 2003 that state regulators wanted contaminated
soils from the West POL Yard (stockpiled by a previous contractor)
disposed of no later than April 4, 2003. We began work immediately
and loaded, manifested, hauled, and disposed of over 1,400
tons of contaminated soils. This was completed on March 14,
2003, 2 1/2 weeks ahead of schedule.
Over 30,000 tons of clean soils were backfilled
into open pits from previous remedial actions. This was accomplished
prior to additional soil excavation activities to provide
stockpiling areas and equipment staging. We excavated over
10,000 tons of soil while terracing the excavations in preparation
for removing the underlying contaminated soil lenses. We
worked closely with the installation to meet the State Regulators
requirements and avoid an NOV for the installation.
Bhate's performance
is outstanding. Their team-oriented approach is focused on
finding solutions for our remediation, compliance, engineering/design,
and pollution prevention challenges here at Holloman. Bhate's
commitment to quality and their responsiveness sets them apart
from their competition. Through their knowledge of our program
and their mannered professionalism, they quickly fostered
a strong working relationship with the New Mexico Environment
Department that has kept Holloman AFB as the single federal
facility in New Mexico operating without the threat of a consent
order. Their experience as a successful small disadvantaged
business has been instrumental in integrating local labor
and small businesses into a cohesive environmental team. I
wholeheartedly recommend Bhate as your environmental contractor
of choice.
Mr. Dan Holmquist, PE,
Restoration Program Manager, Holloman AFB
Site
SS-17; BX Service Station Soil Disposal
In July 2003, Bhate was tasked with providing remedial
alternatives and remedial design for Site SS-17 (former BX
service station) at Holloman AFB. The 2-acre site is located
in a densely populated area of the base and was contaminated
with gasoline and diesel fuel resulting from leaks in fuel
storage and distribution systems at the service station. The
existing soil vapor extraction (SVE) system installed at the site has been inactive for 2
years as asymptotic conditions exist. However, from the soil
and groundwater data collected during the remedial alternatives
process, we concluded that closure of the site would require
additional soil remediation.
After reviewing the available data, we recommended
that the existing SVE remedial approach be abandoned due to
the permeability-limited hydrogeology of the site and cost
/ schedule associated with its continued operation. This
combination of site conditions drove Bhate to develop a value
engineered remedial design process that would greatly reduce
remediation time and cost. The process which was developed
with regulator and stakeholder input, comprises excavation
of the soil to the water table (~ 8 ft) followed by on site
treatment at the FT-31 Land Farm.
OWS
Removals
Bhate self-performed the excavation, removal, clean closure
sampling, backfilling, and site restoration at four OWS locations
at Holloman AFB (HAFB). The work involved the draining and capping
of lines, fluid removal and disposal of tank contents, pavement/concrete
cutting, excavation, removal and disposal of the OWS and coordination
with flight operations at two locations.
One of the OWS vaults removed was estimated
to weigh 15 tons and required an overhead crane that was borrowed
from HAFB at no cost to the project due to the well established
relationship our team enjoys with base personnel. All of the
concrete OWS were transported to the HAFB construction debris
reuse area where they will be recycled into base course for
future construction projects. This effort avoids additional
disposal cost (tipping fee) and provides the facility with
a future P2 credit. The completion of this project in a one
week time frame illustrates how Bhate was able to outperform
schedule and budget requirements due to a well managed field
team.
Construction
and Demolition Debris Recycling at the Reuse Area
The scope of this P2 project involved the size reduction of
concrete and asphalt debris for recycling purposes with the HAFB Reuse Area.
The concrete and asphalt debris was generated over a number
of years through HAFB demolition and construction activities.
The primary means of debris sizing was through course sizing
using demolition attachments on a tracked excavator and final
processing with a mobilized rock crushing plant. Final material
size specified was 1 inch minus.
An estimated
200,000 tons of debris were scattered across the 10-acre reuse
area presenting challenging initial site conditions.
Using GPS to map the area, Bhate completed a sorting and relocation
effort such that a rock crushing plant could be mobilized and
efficiently operated to its maximum capacity. We
processed ~90,000 tons of concrete/ asphalt debris during
a 4 month period from November 2003 through February
2004. The efficient execution of this project provided a cost
savings of approximately $7/ton when compared to conventional
transport and disposal fees to the county landfill. This
method resulted in saving of approximately $630,000 for the
government. The recycled and sized material is made
available for future construction projects at HAFB
as well as the local community. It has also been used to provide
P2 credits on environmental remediation projects where it
has been used as clean fill material for excavations.
|